Pular para o conteúdo
Logotipo Altus Logotipo Altus
Products
Segments
Solutions
Company
Support
Contact
Blog
Knowledge Base
PT
Produtos

Our Products

An exclusive combination of equipment that combines high performance and competitiveness to overcome the challenges of Industry 4.0

    • Control and I/O
    • PLC
    • I/O Systems
    • RTU
    • Terminals
    • HMI
    • Softwares
    • PLC Programming
    • SCADA
    • Asset Management
    • Data Acquisition and Communication
    • Network Converters
    • Gateways
    • Datalogger
    • Industrial Switches
    • Drive and Movement
    • Frequency Inverters
    • Servo Drive
    • Instrumentation
    • Position
    • Pressure
    • Temperature
Segmentos

Industries we serve

At Altus, we have the necessary know-how to provide integrated systems for the most varied demands of the industrial market

    • Oil & Gas
    • Offshore
    • Refine
    • Electrical Energy
    • Hydro Power
    • Solar Power
    • Wind Power
    • Process Industry
    • Water & Wastewater
    • Metals & Mining
    • Sugar & Ethanol
    • Pulp & Paper
    • Agroindustry
    • Chemical
    • Marine
    • Manufacturing Industry
    • Food & Beverage
    • Pharmaceutical & Healthcare
    • Textile
    • Automotive
    • Plastic
    • Infrastructure
    • Subways & Railways
    • Highways & Tunnels
    • BMS
Soluções

Solutions

Discover our solutions and discover how our expertise can help boost your business performance

  • CSS Offshore
  • DCS for Hydroelectric Plants
  • AutobaseWEB
  • Photovoltaic Plants
  • Machine Manufacturers
  • Cybersecurity
Empresa

Company

See how we have become a reference in the automation market over the course of our more than 40 years

  • The Company
  • Headquarters
Suporte

Support

We are 100% available to solve problems, answer questions and help you optimize the performance of your application.

  • Support Center
  • Downloads
  • Knowledge Base
Contato

Contact

Get to know our units and find out where to find our sales representatives throughout Brazil

  • Contact
  • Products
    • Control and I/O
      • PLC
      • I/O Systems
      • RTU
    • Data Acquisition and Communication
      • Converters
    • Operating Terminals
    • Movement and Actuation
    • Softwares
    • Instrumentation
    • Components
    • Control Panels
  • Segments
    • Oil and Gas
      • Offshore
      • Refine
    • Electrical Energy
      • Hydro Power
      • Wind power
      • Solar Power
    • Process Industry
      • Sugar and Ethanol
      • Agroindustry
      • Marine
      • Metals and Mining
      • Pulp and Paper
      • Chemical
      • Water and Wastewater
    • Manufacturing Industry
      • Food and Beverage
      • Automotive
      • Pharmaceutical and Healthcare
      • Plastic
    • Infrastructure
      • Subways and Railways
      • Building management
      • Highways and Tunnels
  • Solutions
    • AutobaseWEB
    • Machine Manufacturers
    • CSS Offshore
    • DCS for Hydroelectric Plants
    • Cybersecurity
    • Photovoltaic Power Plant
  • Suport
    • Support Center
    • Download Center
    • Knowledge base
  • Blog
  • Headquarters
  • PT

Categories:

  • Success Stories
  • Trade Fairs & Events
  • Institutional
  • Perspectives
  • Products
  • Projects
  • Success Stories
  • Trade Fairs & Events
  • Institutional
  • Perspectives
  • Products
  • Projects
Blog

Before powering up the machine: how FAT helps prevent issues in industrial automation

Before powering up the machine: how FAT helps prevent issues in industrial automation

As you may have already noticed across the industrial landscape, automation systems are growing increasingly complex as technologies evolve. This demands ever-greater precision in engineering, network infrastructure, and software programming, even before any machine or panel is energized. Operations involving PLCs, high-speed networks, HMIs, SCADA systems, and distributed architectures require rigorous validation methods before going into operation.

To prevent issues at the exact moment when everything needs to run in sync, there is the Factory Acceptance Test (FAT). It ensures operational safety and prevents unexpected costs and downtime during system startup.

Originally created to verify the physical and electrical compliance of control panels, FAT has evolved into a preventive engineering stage. Within a modern Operational Technology (OT) architecture, it serves as quality assurance, where hardware, software, and control logic undergo operational stress simulations in a controlled environment. Conducting FAT prior to field deployment protects the entire project and safeguards the integrity of both assets and the teams involved. Throughout this article, discover how it can help prevent issues in your automation systems.

The role of FAT in the lifecycle of an automation project

The Factory Acceptance Test (FAT) is the formal validation in which the technology supplier or systems integrator demonstrates to the client that the developed solution meets the contracted technical specifications. The process takes place at the manufacturer’s or panel builder’s facility, immediately after manufacturing is completed and the application software is loaded onto the controllers, but always prior to shipping and installation at the client’s plant.

The mechanics of FAT rely on rigorous simulation of the industrial process, without requiring inputs, raw materials, or the presence of the final machine. Using test benches, signal generators, and simulation software, the system’s inputs and outputs are stimulated to verify the response of control algorithms, safety interlocks, and the navigability of the SCADA system.

For engineering governance and management, FAT turns uncertainties into verifiable variables. It bridges the gap between the theoretical design phase, represented by the User Requirements Specification (URS) and the Functional Design Specification (FDS), and physical execution at the plant. As a result, specification deviations are resolved while the supplier’s resources are still readily available.

FAT structure: what is required to perform the test

FAT involves the thorough validation of four pillars of industrial automation: electrical hardware, input/output mapping, communication architecture, and application software:

Electrical panels and physical hardware integrity

The physical inspection verifies that the panel complies with electrical schematics and safety standards such as ABNT NBR IEC 61439, NR-10, and NR-12. During this stage, dimensions, component layout, wiring quality, terminal connection torque, and wire marker identification are evaluated. It is also verified that thermal protection, grounding, and surge protection systems have been properly implemented. Finally, electrical continuity and insulation resistance tests confirm that future energizations will be carried out safely.

Input/Output (I/O) mapping and controllers

Point-to-point I/O testing bridges the gap between panel hardware and controller software. Using signal sources and simulators, each channel is triggered individually. For analog inputs, signals are injected at 0%, 25%, 50%, 75%, and 100% of the engineering scale. This makes it possible to calibrate scaling conversions in the PLC, verify alarm limits, and confirm wire-break or short-circuit diagnostics, leveraging the built-in diagnostic features of the control platform used.

Industrial network architecture and cybersecurity

The communication infrastructure undergoes physical and logical integrity analyses. Network topology (ring, star, or bus) and proper data exchange across protocols such as PROFINET, EtherNet/IP, Modbus, and EtherCAT are evaluated. In high-criticality systems, network and processor redundancy mechanisms are also tested, measuring switchover times to ensure zero data loss. From a cybersecurity standpoint, and in alignment with the ISA/IEC 62443 standard, switches, Zone and Conduit segmentation, and firewall rules are verified.

Control logic, interlocks, and operator screens

Software validation is the most intensive stage of FAT. Control algorithms programmed in the PLC are tested against all process conditions, including edge cases and fault states. Startup and shutdown routines, machine safety interlocks, operating mode management (Manual, Automatic, and Maintenance), and recipe sequencing are evaluated. In parallel, the HMI and SCADA system undergo auditing to verify screen accuracy, alarm message clarity in accordance with the ANSI/ISA-18.2 standard, historical trend logging, and user access profile management.

Without FAT, system startup costs more, carries higher risks, and falls behind schedule

Skipping the FAT stage to speed up the delivery date is a decision that can, and frequently does, lead to substantial losses. In systems engineering, the rule of escalating defect correction costs demonstrates that the investment required to fix an issue grows exponentially with each phase the project advances.

When a system is shipped to the field without undergoing a structured FAT, commissioning ends up absorbing the resolution of basic wiring errors, software bugs, network addressing mistakes, and firmware incompatibilities. Resolving these pending issues in the field costs significantly more for several reasons: limited access to tools, the need to urgently dispatch specialists, adverse working conditions, and strict downtime constraints imposed by plant operations. Here is a closer look:

OperationFailure identified and resolved during FATFailure identified
in the field
Correction costLow: Adjustments resolved in a bench environment without extra mobilization.Critical: Costs multiplied by deployed field teams and overtime downtime hours.
Schedule impactMinimal: Deviations corrected during the supplier’s scheduled integration window.Severe: Startup delays, missed deadlines, and contractual penalties.
AvailabilityHigh: Immediate access to design engineers, test benches, and manufacturer support.Low: Restricted access to tools, limited connectivity, and remote-only support.
Safety riskNone: Simulated environment with no live power or real mechanical load.High: Risk of equipment damage, physical injuries, or environmental incidents.
Software change managementSafe: Streamlined version control within a controlled development environment.Complex: Risk of version mismatch between the code running on the PLC and project documentation.

Beyond direct financial losses, skipping FAT also creates indirect impacts. These include reduced component lifespan, caused by improper actuations during field testing, and strained relationships between the systems integrator and the end client.

Global engineering standards for FAT: what you need to know

Conducting a Factory Acceptance Test (FAT) must follow international guidelines that standardize everything from test scripts to punch-list and deviation forms.

ABNT NBR IEC 62381 is the primary reference for acceptance testing in process industry automation systems. It specifies the methodology for drafting FAT, SAT (Site Acceptance Test), and SIT (Site Integration Test) procedures, and defines initial documentation, test forms, and the punch-list closeout process.

When an application involves protecting human life and the environment, ABNT NBR IEC 61511 and IEC 61508 come into play, governing the verification of Safety Instrumented Systems (SIS). During the FAT of an SIS, every Safety Instrumented Function (SIF) must have its logic and Safety Integrity Level (SIL) validated without exception. This ensures the system reaches its designed safe state in an emergency.

In operational alarm management, ANSI/ISA-18.2 establishes the rules for evaluating alarm rationalization in the SCADA system during FAT. The goal is to prevent alarm flooding and ensure that only actionable messages reach the operator’s screen.

Finally, at the cybersecurity layer, ISA/IEC 62443 guides the commissioning of information security. It ensures the implementation of the Zones and Conduits model and the verification of Target Security Levels (SL-T) before the panel is shipped.

How Altus’ technology makes FAT more efficient

FAT efficiency increases when the engineering team uses platforms with native simulation capabilities and advanced diagnostics. At Altus, we offer a portfolio that streamlines every stage of the test.

On the software side, the MasterTool X and MasterTool IEC XE programming environments, built on the CODESYS platform, bring together a robust set of engineering tools:

Built-in simulation tool: Engineers can run and validate algorithms developed in all six languages of the IEC 61131-3 standard directly on a computer, without needing to connect a physical CPU. This enables early logic debugging before the on-site FAT with the client.

Advanced diagnostics and retentive logs: MasterTool automatically records event logs and actions executed by both the developer and the CPU in retentive memory. During FAT, these records provide full traceability to audit application behavior.

Modularity and reuse via function blocks: Engineers can build and validate custom, object-oriented Function Block libraries, accelerating the verification of repetitive logic during I/O testing.

At the hardware layer, Nexto Series controllers are engineered to simplify validation throughout the entire FAT:

Native diagnostics on I/O modules: Nexto NX modules feature LED status indicators alongside diagnostics displayed directly in the application, pinpointing bus discrepancies, overcurrent, or broken wires. This streamlines debugging during bench testing.

Multi-protocol support and IIoT connectivity: Configuring OPC UA, MQTT, EtherCAT, and industrial Ethernet on the same CPU is straightforward, simplifying integration testing between the PLC, the SCADA system, databases (via the MSSQL_CLIENT block), and cloud solutions during FAT.

Maintainability and hot-swapping: The Nexto NX architecture allows modules to be removed and replaced while the bus remains energized. This capability can be tested during FAT to verify the availability rates required by the project.

As we have seen throughout this article, the Factory Acceptance Test is the technical investment with the highest preventive return in an industrial automation project. When equipment and systems arrive at the plant fully tested, approved, and compliant with required standards, manufacturers reduce risk and eliminate rework, resulting in faster, safer, and more efficient plant startups.

What you will find in this article

Share

Learn more

Before powering up the machine: how FAT helps prevent issues in industrial automation

Before powering up the machine: how FAT helps prevent issues in industrial automation

Implementing FAT prior to field mobilization protects the project as a whole. Discover how it can help prevent issues in...
Leia mais
Machine Learning and AI are not the same thing: understand the differences and types of applications

Machine Learning and AI are not the same thing: understand the differences and types of applications

AI and Machine Learning are frequently treated as synonyms, as if they were the exact same thing. This confusion obscures...
Leia mais
Altus expands operations in Europe

Altus expands operations in Europe

We have great news for your next automation project: we now offer direct local logistics and invoicing in Germany.
Leia mais
Altus in the electrical sector: decades of innovation in critical power grids

Altus in the electrical sector: decades of innovation in critical power grids

To meet the sector's requirements, Altus has established a proven track record as a benchmark in automation, process control, and...
Leia mais
Practical cybersecurity tips for those with PLCs in operation

Practical cybersecurity tips for those with PLCs in operation

Discover the JBS case and see, in practice, how to protect your application from silent threats that can cause severe...
Leia mais
Altus celebrates 44 years of taking Brazilian automation from the pre-salt layer to renewable hydrogen

Altus celebrates 44 years of taking Brazilian automation from the pre-salt layer to renewable hydrogen

Since our founding on October 26, 1982, we have established ourselves as one of the most prominent companies in the...
Leia mais

Phone: +55 51 3589 9500

E-mail: support@altusautomation.com

Mon–Fri: 8AM–10PM | Sat: 8AM–5PM (GMT-3) | Closed Sundays & holidays.

 

SEGMENTS
  • Oil and Gas
  • Electric Power
  • Process Industry
  • Manufacturing Industry
  • Infrastructure
  • Oil and Gas
  • Electric Power
  • Process Industry
  • Manufacturing Industry
  • Infrastructure
SOLUTIONS
  • AutobaseWEB
  • Machine Manufacturers
  • CSS Offshore
  • DCS for Hydroelectric Plants
  • Solar Power
  • AutobaseWEB
  • Machine Manufacturers
  • CSS Offshore
  • DCS for Hydroelectric Plants
  • Solar Power
CUSTOMER AREA
  • Documentation
  • Tutorials
  • Documentation
  • Tutorials
  • Company
  • Technical Assistance
  • Contact Us
  • Company
  • Technical Assistance
  • Contact Us
PRODUCTS
CONTROL AND I/O
  • PLC
  • I/O Systems
  • RTU
  • PLC
  • I/O Systems
  • RTU
TERMINALS
  • HMI
  • HMI
SOFTWARE
  • PLC Programming
  • SCADA
  • Asset Management
  • PLC Programming
  • SCADA
  • Asset Management
DATA ACQUISITION AND COMMUNICATION
  • Network Converters
  • Gateways
  • Datalogger
  • Industrial Switches
  • Network Converters
  • Gateways
  • Datalogger
  • Industrial Switches
DRIVE AND MOVEMENT
  • Frequency Inverters
  • Servo Drive
  • Frequency Inverters
  • Servo Drive
INSTRUMENTATION
  • Position
  • Pressure
  • Temperature
  • Position
  • Pressure
  • Temperature

© 2026 Altus

Privacy Policy

Criação de sites pela Agência de Marketing Digital Orgânica Digital.